Title: EXECUTION OF ADDITIONAL/ ALTERATION WORKS ASSOCIATED WITH THE ONGOING CONSTRUCTION OF EPE ELDERLY CARE CENTRE
OCID: ocds-5q8fsw-6202250102116
Release Id: 925
see release json

Use the controls below to toggle different perspectives of this project.

Project Overview
Project Overview
Project Name Procuring Entity Project Cost Contractor Year Status Remark Publication Date Project Location
Execution of Additional/ Alteration Works associated with the Ongoing Construction of EPE Elderly Care Centre YOUTH & SOCIAL DEVELOPMENT ₦130,977,283.65 BUHARI SULAIMON & SON LTD 2021 ONGOING 6/6/2022 1:11:11 AM EPE, LAGOS
Release
Initiation Type OCID Buyer Release Tags Relese Date
Tender ocds-5q8fsw-6202250102116 YOUTH & SOCIAL DEVELOPMENT Planning, Tender, Award, Contract, Implementation 06 Jun 2022
Associated Budget
Description MDA Fiscal Period Amount URL
PROCUREMENT PLAN 2021 YOUTH & SOCIAL DEVELOPMENT 2021 FISCAL PERIOD ₦5,134,276,339.00
Project Tender
Title Status Procurement Category Procurement Method Procurement Details Award Criteria Number of Tenderers Minimum Amount Maximum Amount
Execution of Additional/ Alteration Works associated with the Ongoing Construction of EPE Elderly Care Centre Active Works Direct Single bid only 1 ₦130,977,283.65 ₦130,977,283.65
Project Tenderers
Not Available

No tenderers have been published for this project.

Project Award
Title Description Suppliers Status Award Date Total Amount Contract Period
Execution of Additional/ Alteration Works associated with the Ongoing Construction of EPE Elderly Care Centre Execution of Additional/ Alteration Works associated with the Ongoing Construction of EPE Elderly Care Centre No Suppliers assigned Active 30 Sep 2021 ₦130,977,283.65 01 Jan 2021 - 31 Dec 2021
Project Contracts
Award Title Description Status Date Total Value Contract Period
Execution of Additional/ Alteration Works associated with the Ongoing Construction of EPE Elderly Care Centre Execution of Additional/ Alteration Works associated with the Ongoing Construction of EPE Elderly Care Centre Execution of Additional/ Alteration Works associated with the Ongoing Construction of EPE Elderly Care Centre Active 30 Sep 2021 ₦130,977,283.65 01 Jan 2021 - 31 Dec 2021
Planning Details
Budget Rationale
PROCUREMENT PLAN 2021 To make facility available for the elderly.