Use the controls below to toggle different perspectives of this project.
Project Name | Procuring Entity | Project Cost | Contractor | Year | Status | Remark | Publication Date | Project Location | |
---|---|---|---|---|---|---|---|---|---|
Balance Payment of Variation Costs on the Ongoing 32MTPH Rice Mill at Imota | MINISTRY OF AGRICULTURE | ₦1,349,900,736.22 | FAO CONSULTING INTERNATIONAL LIMITED | 2022 | ONGOING | 6/5/2022 3:15:35 PM | IMOTA |
Initiation Type | OCID | Buyer | Release Tags | Relese Date | |
---|---|---|---|---|---|
Tender | ocds-5q8fsw-6202262870221 | MINISTRY OF AGRICULTURE | Planning, Tender, Award, Contract, Implementation | 05 Jun 2022 |
Description | MDA | Fiscal Period | Amount | URL | |
---|---|---|---|---|---|
PROCUREMENT PLAN 2022 | MINISTRY OF AGRICULTURE | 2022 Fiscal period | ₦15,869,936,370.00 |
Title | Status | Procurement Category | Procurement Method | Procurement Details | Award Criteria | Number of Tenderers | Minimum Amount | Maximum Amount | |
---|---|---|---|---|---|---|---|---|---|
Balance Payment of Variation Costs on the Ongoing 32MTPH Rice Mill at Imota | Active | Works | Direct | Best value to government | 1 | ₦1,349,900,736.22 | ₦1,349,900,736.22 |
No tenderers have been published for this project.
Title | Description | Suppliers | Status | Award Date | Total Amount | Contract Period | |
---|---|---|---|---|---|---|---|
Balance Payment of Variation Costs on the Ongoing 32MTPH Rice Mill at Imota | Balance Payment of Variation Costs on the Ongoing 32MTPH Rice Mill at Imota | No Suppliers assigned | Active | 13 Jan 2022 | ₦1,349,900,736.22 | 01 Jan 2022 - 31 Dec 2022 |
Award | Title | Description | Status | Date | Total Value | Contract Period | |
---|---|---|---|---|---|---|---|
Balance Payment of Variation Costs on the Ongoing 32MTPH Rice Mill at Imota | Balance Payment of Variation Costs on the Ongoing 32MTPH Rice Mill at Imota | Balance Payment of Variation Costs on the Ongoing 32MTPH Rice Mill at Imota | Active | 13 Jan 2022 | ₦1,349,900,736.22 | 01 Jan 2022 - 31 Dec 2022 |
Budget | Rationale | |
---|---|---|
PROCUREMENT PLAN 2022 |