Use the controls below to toggle different perspectives of this project.
Project Name | Procuring Entity | Project Cost | Contractor | Year | Status | Remark | Publication Date | Project Location | |
---|---|---|---|---|---|---|---|---|---|
Construction of Sleeping Quarters at the Three Asphalt Plants (Ojodu, Imota & Badagry) Ojodu Asphalt Main Yard, Mechanical Workshop, Toilets and Store Reservation. | PUBLIC WORKS CORPORATION | ₦229,124,263.54 | TRUSSET & FUSSET INTEGRATED SERVICES LIMITED | 2021 | ON-GOING | 6/1/2022 2:13:53 PM | LAGOS |
Initiation Type | OCID | Buyer | Release Tags | Relese Date | |
---|---|---|---|---|---|
Tender | ocds-5q8fsw-6202250174161 | PUBLIC WORKS CORPORATION | Planning, Tender, Award, Contract, Implementation | 01 Jun 2022 |
Description | MDA | Fiscal Period | Amount | URL | |
---|---|---|---|---|---|
PROCUREMENT PLAN 2021 | PUBLIC WORKS CORPORATION | 2021 FISCAL PERIOD | ₦8,982,634,125.87 |
Title | Status | Procurement Category | Procurement Method | Procurement Details | Award Criteria | Number of Tenderers | Minimum Amount | Maximum Amount | |
---|---|---|---|---|---|---|---|---|---|
Construction of Sleeping Quarters at the Three Asphalt Plants (Ojodu, Imota & Badagry) Ojodu Asphalt Main Yard, Mechanical Workshop, Toilets and Store Reservation | Active | Works | Selective | Lowest cost | 3 | ₦229,124,263.54 | ₦229,124,263.54 |
No tenderers have been published for this project.
Title | Description | Suppliers | Status | Award Date | Total Amount | Contract Period | |
---|---|---|---|---|---|---|---|
Construction of Sleeping Quarters at the Three Asphalt Plants (Ojodu, Imota & Badagry) Ojodu Asphalt Main Yard, Mechanical Workshop, Toilets and Store Reservation | Construction of Sleeping Quarters at the Three Asphalt Plants (Ojodu, Imota & Badagry) Ojodu Asphalt Main Yard, Mechanical Workshop, Toilets and Store Reservation | No Suppliers assigned | Active | 28 Jun 2021 | ₦229,124,263.54 | 01 Jan 2021 - 31 Dec 2021 |
Award | Title | Description | Status | Date | Total Value | Contract Period | |
---|---|---|---|---|---|---|---|
Construction of Sleeping Quarters at the Three Asphalt Plants (Ojodu, Imota & Badagry) Ojodu Asphalt Main Yard, Mechanical Workshop, Toilets and Store Reservation | Construction of Sleeping Quarters at the Three Asphalt Plants (Ojodu, Imota & Badagry) Ojodu Asphalt Main Yard, Mechanical Workshop, Toilets and Store Reservation | Construction of Sleeping Quarters at the Three Asphalt Plants (Ojodu, Imota & Badagry) Ojodu Asphalt Main Yard, Mechanical Workshop, Toilets and Store Reservation | Active | 28 Jun 2021 | ₦229,124,263.54 | 01 Jan 2021 - 31 Dec 2021 |
Budget | Rationale | |
---|---|---|
PROCUREMENT PLAN 2021 | To reduce manhours losses due to travel time of Engineers, operatives and asphalt production vrew to various sites from the Corporation headquarters and their various homes |