Project Release Details

Title: RENOVATION OF BURNT PRINCIPAL OFFICE AT EPE SENIOR GRAMMAR SCHOOL, EPE LGA
OCID: ocds-5q8fsw-6202285280738
Release Id: 749
see release json

Use the controls below to toggle different perspectives of this project.

Project Overview
Project Overview
Project Name Procuring Entity Project Cost Contractor Year Status Remark Publication Date Project Location
RENOVATION OF BURNT PRINCIPAL OFFICE AT EPE SENIOR GRAMMAR SCHOOL, EPE LGA SPECIAL COMMITTEE ON REHABILITATION OF PUBLIC SCHOOLS ₦36,962,922.01 MICHELAD NIGERIA LIMITED 2021 ONGOING 6/1/2022 11:20:12 AM EPE LGA
Release
Initiation Type OCID Buyer Release Tags Relese Date
Tender ocds-5q8fsw-6202285280738 SPECIAL COMMITTEE ON REHABILITATION OF PUBLIC SCHOOLS Planning, Tender, Award, Contract, Implementation 01 Jun 2022
Associated Budget
Description MDA Fiscal Period Amount URL
PROCUREMENT PLAN SPECIAL COMMITTEE ON REHABILITATION OF PUBLIC SCHOOLS 2021 FISCAL PERIOD ₦6,975,865,000.00
Project Tender
Title Status Procurement Category Procurement Method Procurement Details Award Criteria Number of Tenderers Minimum Amount Maximum Amount
RENOVATION OF BURNT PRINCIPAL OFFICE AT EPE SENIOR GRAMMAR SCHOOL, EPE LGA Active Works Selective Lowest cost 3 ₦36,962,922.01 ₦36,962,922.01
Project Tenderers
Not Available

No tenderers have been published for this project.

Project Award
Title Description Suppliers Status Award Date Total Amount Contract Period
RENOVATION OF BURNT PRINCIPAL OFFICE AT EPE SENIOR GRAMMAR SCHOOL, EPE LGA RENOVATION OF BURNT PRINCIPAL OFFICE AT EPE SENIOR GRAMMAR SCHOOL, EPE LGA No Suppliers assigned Active 02 Nov 2021 ₦36,962,922.01 01 Jan 2021 - 31 Dec 2021
Project Contracts
Award Title Description Status Date Total Value Contract Period
RENOVATION OF BURNT PRINCIPAL OFFICE AT EPE SENIOR GRAMMAR SCHOOL, EPE LGA RENOVATION OF BURNT PRINCIPAL OFFICE AT EPE SENIOR GRAMMAR SCHOOL, EPE LGA RENOVATION OF BURNT PRINCIPAL OFFICE AT EPE SENIOR GRAMMAR SCHOOL, EPE LGA Active 02 Nov 2021 ₦36,962,922.01 01 Jan 2021 - 31 Dec 2021
Planning Details
Budget Rationale
PROCUREMENT PLAN To make reading environment Conducive for learning