Use the controls below to toggle different perspectives of this project.
Project Name | Procuring Entity | Project Cost | Contractor | Year | Status | Remark | Publication Date | Project Location | |
---|---|---|---|---|---|---|---|---|---|
PRELIMINARY MAPPING & ASSESSMENT OF JETTIES/TERMINALS - ILAJE JETTY, BARIGA | LAGOS STATE WATERWAYS AUTHORITY | ₦9,995,450.00 | OEA CONSULTS LTD | 2021 | COMPLETED | 5/25/2022 2:31:10 PM | BARIGA, LAGOS |
Initiation Type | OCID | Buyer | Release Tags | Relese Date | |
---|---|---|---|---|---|
Tender | ocds-5q8fsw-5202284405865 | LAGOS STATE WATERWAYS AUTHORITY | Planning, Tender, Award, Contract, Implementation | 25 May 2022 |
Description | MDA | Fiscal Period | Amount | URL | |
---|---|---|---|---|---|
PROCUREMENT PLAN 2021 | LAGOS STATE WATERWAYS AUTHORITY | 2021 FISCAL PERIOD | ₦4,204,616,989.00 |
Title | Status | Procurement Category | Procurement Method | Procurement Details | Award Criteria | Number of Tenderers | Minimum Amount | Maximum Amount | |
---|---|---|---|---|---|---|---|---|---|
PRELIMINARY MAPPING & ASSESSMENT OF JETTIES/TERMINALS - ILAJE JETTY, BARIGA | Complete | Works | Direct | Single bid only | 1 | ₦9,995,450.00 | ₦9,995,450.00 |
No tenderers have been published for this project.
Title | Description | Suppliers | Status | Award Date | Total Amount | Contract Period | |
---|---|---|---|---|---|---|---|
PRELIMINARY MAPPING & ASSESSMENT OF JETTIES/TERMINALS - ILAJE JETTY, BARIGA | PRELIMINARY MAPPING & ASSESSMENT OF JETTIES/TERMINALS - ILAJE JETTY, BARIGA | No Suppliers assigned | Active | 04 Feb 2021 | ₦9,995,450.00 | 01 Jan 2021 - 31 Dec 2021 |
Award | Title | Description | Status | Date | Total Value | Contract Period | |
---|---|---|---|---|---|---|---|
PRELIMINARY MAPPING & ASSESSMENT OF JETTIES/TERMINALS - ILAJE JETTY, BARIGA | PRELIMINARY MAPPING & ASSESSMENT OF JETTIES/TERMINALS - ILAJE JETTY, BARIGA | PRELIMINARY MAPPING & ASSESSMENT OF JETTIES/TERMINALS - ILAJE JETTY, BARIGA | Active | 04 Feb 2021 | ₦9,995,450.00 | 01 Jan 2021 - 31 Dec 2021 |
Budget | Rationale | |
---|---|---|
PROCUREMENT PLAN 2021 | GATHERING OF DATA TOWARDS UPGRADE OF JETTIES/TERMINALS |