Project Name Procuring Entity Project Cost Contractor Year Status Remark Publication Date Project Location
CONSTRUCTION OF APAKALA DOWNSTREAM COLLECTOR DRAIN, EPE OFFICE OF DRAINAGE SERVICES & WATER RESOURCES ₦45,375,701.54 SEGNES ENGINEERING COMPANY LIMITED 2022 ONGOING 5/23/2023 10:21:19 AM EPE
Release
Initiation Type OCID Buyer Release Tags Relese Date
Tender ocds-5q8fsw-5202373875718 OFFICE OF DRAINAGE SERVICES & WATER RESOURCES Planning, Tender, Award, Contract, Implementation 23 May 2023
Associated Budget
Description MDA Fiscal Period Amount URL
PROCUREMENT PLAN 2022 OFFICE OF DRAINAGE SERVICES & WATER RESOURCES 2022 Fiscal period ₦4,029,852,859.00 NIL
Project Tender
Title Status Procurement Category Procurement Method Procurement Details Award Criteria Number of Tenderers Minimum Amount Maximum Amount
CONSTRUCTION OF APAKALA DOWNSTREAM COLLECTOR DRAIN, EPE Active Works Direct Single bid only 1 ₦45,375,701.54 ₦45,375,701.54
Project Tenderers
Not Available

No tenderers have been published for this project.

Project Award
Title Description Suppliers Status Award Date Total Amount Contract Period
CONSTRUCTION OF APAKALA DOWNSTREAM COLLECTOR DRAIN, EPE CONSTRUCTION OF APAKALA DOWNSTREAM COLLECTOR DRAIN, EPE No Suppliers assigned Active 13 Jul 2022 ₦45,375,701.54 01 Jan 2022 - 31 Dec 2022
Project Contracts
Award Title Description Status Date Total Value Contract Period
CONSTRUCTION OF APAKALA DOWNSTREAM COLLECTOR DRAIN, EPE CONSTRUCTION OF APAKALA DOWNSTREAM COLLECTOR DRAIN, EPE CONSTRUCTION OF APAKALA DOWNSTREAM COLLECTOR DRAIN, EPE Active 13 Jul 2022 ₦45,375,701.54 01 Jan 2022 - 31 Dec 2022
Planning Details
Budget Rationale
PROCUREMENT PLAN 2022 The award of these contracts would help reduce the effect of flooding due to rainfall in these areas