Project Name | Procuring Entity | Project Cost | Contractor | Year | Status | Remark | Publication Date | Project Location | |
---|---|---|---|---|---|---|---|---|---|
REHABILITATION/UPGRADING OF ETI-OSA/LEKKI/EPE EXPRESSWA - (PHASE IIA) FROM ELEKO JUNCTION THROUGH AWOYAYA TO GREENSPRING AND THE MAJEK AND OGIDAN AXIS (18.6KM) IN ETI-OSA AND IBEJU-LEKKI LGA | OFFICE OF INFRASTRUCTURE | ₦106,489,578,350.78 | CRANEBURG CONSTRUCTION LIMITED | 2022 | ONGOING | 5/12/2023 11:39:30 AM | IBEJU-LEKKI |
Initiation Type | OCID | Buyer | Release Tags | Relese Date | |
---|---|---|---|---|---|
Tender | ocds-5q8fsw-5202326558664 | OFFICE OF INFRASTRUCTURE | Planning, Tender, Award, Contract, Implementation | 12 May 2023 |
Description | MDA | Fiscal Period | Amount | URL | |
---|---|---|---|---|---|
PROCUREMENT PLAN 2022 | OFFICE OF INFRASTRUCTURE | 2022 Fiscal period | ₦28,305,386,341.00 | NIL |
Title | Status | Procurement Category | Procurement Method | Procurement Details | Award Criteria | Number of Tenderers | Minimum Amount | Maximum Amount | |
---|---|---|---|---|---|---|---|---|---|
REHABILITATION/UPGRADING OF ETI-OSA/LEKKI/EPE EXPRESSWA - (PHASE IIA) FROM ELEKO JUNCTION THROUGH AWOYAYA TO GREENSPRING AND THE MAJEK AND OGIDAN AXIS (18.6KM) IN ETI-OSA AND IBEJU-LEKKI LGA | Active | Works | Direct | Single bid only | 1 | ₦106,489,578,350.78 | ₦106,489,578,350.78 |
No tenderers have been published for this project.
Title | Description | Suppliers | Status | Award Date | Total Amount | Contract Period | |
---|---|---|---|---|---|---|---|
REHABILITATION/UPGRADING OF ETI-OSA/LEKKI/EPE EXPRESSWA - (PHASE IIA) FROM ELEKO JUNCTION THROUGH AWOYAYA TO GREENSPRING AND THE MAJEK AND OGIDAN AXIS (18.6KM) IN ETI-OSA AND IBEJU-LEKKI LGA | REHABILITATION/UPGRADING OF ETI-OSA/LEKKI/EPE EXPRESSWA - (PHASE IIA) FROM ELEKO JUNCTION THROUGH AWOYAYA TO GREENSPRING AND THE MAJEK AND OGIDAN AXIS (18.6KM) IN ETI-OSA AND IBEJU-LEKKI LGA | No Suppliers assigned | Active | 20 Oct 2022 | ₦106,489,578,350.78 | 01 Jan 2022 - 31 Dec 2022 |
Award | Title | Description | Status | Date | Total Value | Contract Period | |
---|---|---|---|---|---|---|---|
REHABILITATION/UPGRADING OF ETI-OSA/LEKKI/EPE EXPRESSWA - (PHASE IIA) FROM ELEKO JUNCTION THROUGH AWOYAYA TO GREENSPRING AND THE MAJEK AND OGIDAN AXIS (18.6KM) IN ETI-OSA AND IBEJU-LEKKI LGA | REHABILITATION/UPGRADING OF ETI-OSA/LEKKI/EPE EXPRESSWA - (PHASE IIA) FROM ELEKO JUNCTION THROUGH AWOYAYA TO GREENSPRING AND THE MAJEK AND OGIDAN AXIS (18.6KM) IN ETI-OSA AND IBEJU-LEKKI LGA | REHABILITATION/UPGRADING OF ETI-OSA/LEKKI/EPE EXPRESSWA - (PHASE IIA) FROM ELEKO JUNCTION THROUGH AWOYAYA TO GREENSPRING AND THE MAJEK AND OGIDAN AXIS (18.6KM) IN ETI-OSA AND IBEJU-LEKKI LGA | Active | 20 Oct 2022 | ₦106,489,578,350.78 | 01 Jan 2022 - 31 Dec 2022 |
Budget | Rationale | |
---|---|---|
PROCUREMENT PLAN 2022 | TO FAST TRACK PROCUREMENT PROCESS DUE TO DEPLORABLE STATE OF THE ROAD |