Project Name | Procuring Entity | Project Cost | Contractor | Year | Status | Remark | Publication Date | Project Location | |
---|---|---|---|---|---|---|---|---|---|
Relocation of Power cable and property situated at Block 69A,26,27 & 28 and Admiralty Lekki Pennisula scheme1 in Lagos state | MINISTRY OF ENERGY & MINERAL RESOURCES DEV | ₦218,270,000.00 | OJITE TECHINICAL SERVICES LIMITED | 2022 | COMPLETED | 3/24/2023 9:53:09 AM | LEKKI, LAGOS |
Initiation Type | OCID | Buyer | Release Tags | Relese Date | |
---|---|---|---|---|---|
Tender | ocds-5q8fsw-3202353461737 | MINISTRY OF ENERGY & MINERAL RESOURCES DEV | Planning, Tender, Award, Contract, Implementation | 24 Mar 2023 |
Description | MDA | Fiscal Period | Amount | URL | |
---|---|---|---|---|---|
PROCUREMENT PLAN 2022 | MINISTRY OF ENERGY & MINERAL RESOURCES DEV | 2022 Fiscal period | ₦27,212,600,517.00 |
Title | Status | Procurement Category | Procurement Method | Procurement Details | Award Criteria | Number of Tenderers | Minimum Amount | Maximum Amount | |
---|---|---|---|---|---|---|---|---|---|
Relocation of Power cable and property situated at Block 69A,26,27 & 28 and Admiralty Lekki Pennisula scheme1 in Lagos state | Active | Works | Selective | Lowest cost | 2 | ₦218,270,000.00 | ₦218,270,000.00 |
No tenderers have been published for this project.
Title | Description | Suppliers | Status | Award Date | Total Amount | Contract Period | |
---|---|---|---|---|---|---|---|
Relocation of Power cable and property situated at Block 69A,26,27 & 28 and Admiralty Lekki Pennisula scheme1 in Lagos state | Relocation of Power cable and property situated at Block 69A,26,27 & 28 and Admiralty Lekki Pennisula scheme1 in Lagos state | No Suppliers assigned | Active | 24 May 2022 | ₦218,270,000.00 | 01 Jan 2022 - 31 Dec 2022 |
Award | Title | Description | Status | Date | Total Value | Contract Period | |
---|---|---|---|---|---|---|---|
Relocation of Power cable and property situated at Block 69A,26,27 & 28 and Admiralty Lekki Pennisula scheme1 in Lagos state | Relocation of Power cable and property situated at Block 69A,26,27 & 28 and Admiralty Lekki Pennisula scheme1 in Lagos state | Relocation of Power cable and property situated at Block 69A,26,27 & 28 and Admiralty Lekki Pennisula scheme1 in Lagos state | Active | 24 May 2022 | ₦218,270,000.00 | 01 Jan 2022 - 31 Dec 2022 |
Budget | Rationale | |
---|---|---|
PROCUREMENT PLAN 2022 | RELOCATION OF OVERHEAD AND UNDERGROUND XLPE CABLES THAT RADIATE FROM EKO ELECTRICITY DISTRIBUTION COMPANY SUBSTATION WITHIN BLOCK 69A AND TRANSVERSE ACROSS PLOTS 26, 27 AND 28 ON ADMIRALTY WAY, LEKKI PENINSULA SCHEME 1 |